Since our last update, engineers have attended site to inspect Lock 46 following a boating incident.
Unfortunately, the lock gate has detached from its fixing. Repairs will involve replacing the anchor plate that has been pulled from the coping stone and reattaching the lock gate on the offside. The works are expected to be completed within the next two to three weeks.
During this period, a detailed repair plan will be developed, the required materials will be ordered, and consultations will take place with our Heritage and Ecology teams to ensure the works can proceed appropriately.
A further update will be provided on or before Wednesday 28 October.