Thu, Oct 8
Further investigations have confirmed that both pumps supporting the Watford Lock Flight have failed. However, while repairs are required, the primary reason for the ongoing closure remains the continued lack of available water, and this is likely to remain the determining factor for some time.
Work is now underway to return the second pump to service. The failure was caused by worn bearings, linked to a significant build-up of silt within the well. Around five tonnes of silt must be removed before repairs can be completed, and specialist contractors have been engaged to carry out this work.
Once the well has been cleared, repairs to the pump will be undertaken. We currently expect this work to be completed within the next three weeks. Further work will then be undertaken to replace the first pump this winter.