Tue, Oct 13
Since our last update, works within the canal have now been successfully completed and the refilling of the canal is underway. The repaired areas will continue to be closely monitored throughout this process.
The removal of the dams is scheduled to take place on Thursday 15 October and Friday 16 October. Once these have been removed, the canal is planned to reopen navigation from 5pm on Friday 16 October.
Our contractor will remain on site following the reopening to complete reinstatement works to the adjoining land and undertake demobilisation activities.
Water levels on the Rochdale Canal will continue to be monitored closely and are expected to remain unaffected by these operations.