Lock 83 to Lock 81, Rochdale Canal

Navigation ClosureCompleted

Lock 83 to Lock 81, Rochdale Canal

Rochdale Canal

Type

Navigation Closure

Reason

Repair

Region

North West

Last update

Tue, Oct 13

Timing

Tue, Mar 31 → Fri, Oct 16

Affected location

Rochdale Canal

Lock 81 Butler Street to Lock 83 Brownsfield

Update history

Tue, Oct 13

Since our last update, works within the canal have now been successfully completed and the refilling of the canal is underway. The repaired areas will continue to be closely monitored throughout this process.

The removal of the dams is scheduled to take place on Thursday 15 October and Friday 16 October. Once these have been removed, the canal is planned to reopen navigation from 5pm on Friday 16 October.

Our contractor will remain on site following the reopening to complete reinstatement works to the adjoining land and undertake demobilisation activities.

Water levels on the Rochdale Canal will continue to be monitored closely and are expected to remain unaffected by these operations.

Thu, Oct 8

Since our last update, our contractors are currently repositioning the flume between the dam sheets, which we are hopeful this will be completed by next week.

Once this has been completed, our contractors will complete the necessary reinstatement works, which includes resurfacing the towpath and demobilising from site.

Water levels on the Rochdale Canal will continue to be monitored closely throughout the works.

A further update will be provided on or before Tuesday, 20 October.

Wed, Sep 23

Since our last update, works to the canal bed and offside washwall are now completed. Works will now commence on the towpath side to repair the leak to the culvert, this will involve repositioning the flume between the dams, which is planned to take place on Thursday, 1 October. Once repairs are competed, the team will begin resurfacing the towpath.

Water levels on the Rochdale Canal will be monitored closely throughout this operation.

Our next update will be provided on or before Thursday, 8 October.

Wed, Sep 9

Since out last update contractors have encountered some unforeseen ground conditions during the excavation works which requires additional engineering assessments to be carried out. Work has now been scheduled to continue on Monday 14 September. Despite this short delay, work on site has continued to make good progress and remains on track to be completed by the end of October. Our next update will be provided on or before Wednesday 23 September.

Wed, Aug 26

Investigation works have now been completed, and our contract partner, JN Bentley, is making good progress with the repair works. The adjacent culvert has been repaired, and backfilling of the excavation is currently underway. Repairs to the canal bed and the sunken towpath will follow. To facilitate the canal bed repair, the flume supplying water downstream will need to be repositioned. Pumps will be on hand throughout this operation to help maintain water levels. Work is progressing well, and completion is currently anticipated towards the end of October 2026. Our teams continue to work hard to maintain water levels and minimise the impact on navigation. We will also continue to monitor levels closely. If you notice any sudden changes in water levels, please contact our North West Customer Support Team on 03030 404040. Our next update will be provided on or before Wednesday 9 September 2026.

Wed, Aug 12

Investigations are currently being carried out to assess the full extent of the damage and establish the repairs required. Once these investigations are completed, permanent repairs will begin to the failed wash wall, the adjacent culvert, and the damaged canal bed below Lock 81 on the Rochdale Canal. Our operational teams continue to carefully manage water levels downstream of the breach. The prolonged dry weather has reduced the amount of water flowing into the canal network, and water is also being lost through the dammed area, making water management particularly challenging. Our teams are working tirelessly to keep the levels from falling and if you notice any sudden changes to call our North West Customer Support Team on 03030 404040. We will continue to monitor water levels closely. Our next update will be provided on or before Wednesday, 26 August.

Wed, Jul 29

Our contractor has now begun work on the permanent repair to the failed wash wall, the adjacent culvert and the damaged canal bed below Lock 81 on the Rochdale Canal. The first stage of the work is to excavate around the damaged culvert so that engineers can fully assess the extent of the damage. Once this investigation is complete, the permanent repairs will begin. The current programme of work is expected to take around 12 weeks, although this may change depending on what is uncovered during the investigation. Our operational teams continue to carefully manage water levels downstream of the breach. The prolonged dry weather has reduced the amount of water flowing into the canal network, and water is also being lost through the dammed area, making water management particularly challenging. Our teams are working tirelessly to keep the levels from falling and if you notice any sudden changes to call our North West Customer Support Team on 03030 404040. We will continue to monitor water levels closely. Our next update will be provided on 12 August 2026.

Fri, Jul 24

Discussions are still ongoing which will enable repairs to take place, however, there are still matters that need to be resolved before works can commence. As a result, the works remain on hold until permission has been granted. We apologise for the continued delay and we thank customers for their patience. As discussions remain ongoing, we anticipate providing a further update on or before Wednesday 29 July.

Fri, Jul 10

Since our previous update, discussions with the neighbouring landowner have continued regarding permission to access the site and carry out the required works from their land, therefore, our team is still unable to proceed with the necessary repairs. We apologise for any inconvenience caused and thank you for your patience while these matters are being resolved. As discussions are ongoing, we anticipate providing a further update regarding the commencement of works on or before Friday, 24 July.

Fri, Jun 26

Discussions are currently progressing with the neighbouring landowner to obtain permission to access the site and commence works from their land. Until such permission is granted, our team is unable to carry out the necessary repairs. We apologise for any inconvenience caused and thank you for your patience while these matters are being resolved. As discussions are ongoing, we anticipate providing a further update regarding the commencement of works on or before Friday 10 July.

Fri, Jun 12

We have undertaken further investigative works in preparation for our contractors commencing works on site. This has included a detailed assessment to ensure that all necessary groundwork is in place ahead of the essential repairs to the canal wash wall and canal bed to be carried out. Discussions are still ongoing with the neighbouring landowner to secure the required access to their land, which is necessary to enable these repair works to proceed. A further update will be provided on or before Friday, 26 June.

Wed, Jun 3

We are currently in discussions with the neighbouring landowner to secure the necessary access to their land, which is required to undertake repairs to the canal wash wall and canal bed, A start date for the repair works will be confirmed once access arrangements have been agreed. A further update will be provided on or before Friday, 12 June.

Mon, May 18

We are continuing to work with the neighbouring land owner and once access agreements are in place we will be able to start the repairs to the canal bed and wash wall. Further updates will be provided on or before Friday 29th May

Fri, May 1

Our engineers have now finished their investigation and design works, and our contractors are in the final stages of preparing to attend site. We are working with the neighbouring land owner and once access agreements are in place will be able to start the repairs to the canal bed and wash wall. Further updates will be provided on or before Friday 15th May

Mon, Apr 20

We have undertaken a CCTV survey of the adjoining third-party assets and identified the main issue; we're now moving into the next stage of work and are preparing the plans and agreements needed to carry out more detailed on‑site investigations. Over the next couple of weeks, our engineers will be carrying out investigations that will include setting up the site to allow excavation work to take place. These investigation works will enable our engineers to finalise the detailed design prior to undertaking the permanent repair work. We will provide a further update on or before 4 May.

Mon, Apr 13

Our teams have been working hard to stabilise water levels along the affected section of the Rochdale Canal. We have seen an encouraging improvement over the weekend and over next few days we expect water levels at New Islington Marina to normalise. Once levels are fully restored, our engineering teams will be able to get started on their detailed investigations. These investigations are thorough and will take several weeks to complete. Following this, we will be able to confirm a programme of repair works. We'll provide a further update on or before 20 April 2026

Wed, Apr 8

Navigation remains closed between Lock 81 and Lock 82 on the Rochdale Canal following the failure of a temporary repair to a culvert. This has resulted in low water levels along this section of the canal, including New Islington Marina. Initial investigations have confirmed that the temporary repair failed due to a combination of factors. Our engineering teams are continuing to investigate these in detail, alongside identifying the requirements for a permanent repair. We understand how unsettling and disruptive reduced water levels can be for our customers. Please be assured that our priority is to protect affected boaters and to restore water levels as safely and quickly as possible. A strong focus remains on returning New Islington Marina to full water levels and improving conditions in the surrounding area. From today, our contractors will be on site to begin work to install temporary dams. These will stabilise the canal and prevent any further loss of water. Once the dam is securely in place, we will carry out a controlled refill of the canal. This process will take several days, but at this stage we expect water levels to begin to normalise by the weekend. In parallel with these immediate actions, the Trust's engineers are also working to confirm ownership of the land adjacent to the site, as liaison with the relevant landowners will be required to plan and deliver a long‑term, permanent repair. A further update will be provided on or before 13 April.

Thu, Apr 2

Our team and engineers have now carried out detailed inspections,and a leak has been identified below Lock 81. We are now planning a method of repair. We will provide further update Friday 17 April Thank you for your understanding and patience