Tue, Oct 13
Following the start of works at Cossington Lock, our teams have encountered several unexpected challenges that have affected progress on site. Difficulties mobilising the works, including access constraints and the need to travel from an alternative base, have reduced the time available for productive work on site.
We are working hard to recover lost time wherever possible. However, despite these efforts, the original programme can no longer be achieved.
As a result, the closure will need to be extended by approximately two weeks. We are currently aiming to reopen the navigation on Friday 6 November 2026.