Between Llangynidr Bridge 131 and Llangattock Bridge 111 (spot dredging north and south of mainline dredge)

AdviceActive

Between Llangynidr Bridge 131 and Llangattock Bridge 111 (spot dredging north and south of mainline dredge)

Monmouthshire & Brecon Canal

Type

Advice

Reason

Information

Region

Wales and South West

Last update

Wed, Apr 15

Timing

Mon, Apr 20

Review expected Mon, Aug 31

Affected location

Monmouthshire & Brecon Canal

Llangattock Bridge 111 to Llangynidr 131

Update history

Wed, Apr 15

Further to the notice below, please see locations for the dredging due to start on the 20th April.

Winding Holes  Winding Hole Panteague Bridge 128.  Winding Hole Aber Howie Bridge 127 Winding Hole Windy Corner Bridge 109   Spot Dredging  Bridge 130, Aberyail  Bridge 120, Baylis Bridge Bridge 119, Folly Bridge  Bridge 117, Dan-Y-Garth  Bridge 116, Ffawyddog  Bridge 115, Upper Yard  Bridge 113, Llwmws Bridge  Bridge 112, Park Bridge

You are welcome to contact us at enquiries.walessouthwest@canalrivertrust.org.uk or 03030 404040 if you would like to discuss this information with a member of our Customer Service Team.

Tue, Apr 14

Further to the notice below, we apologise for the recent delay to the start of dredging.

This is due to essential engineering modifications required to the dredger.

These were identified to prevent potential damage to the canal bed and were necessary to protect the long‑term condition of the waterway.

Whilst this has resulted in a short delay, the contractor is currently on site setting up the compound.

 Dredging is now due to start on the 20th April.

Thank you for your patience.

You are welcome to contact us at enquiries.walessouthwest@canalrivertrust.org.uk or 03030 404040 if you would like to discuss this information with a member of our Customer Service Team.

Tue, Mar 10

Please be advised that mainline dredging will be taking place on the Monmouthshire & Brecon Canal between Llangynidr Bridge 131 and Llangattock Bridge 111 from Monday 16th March for approximately 8 weeks. 

The navigation and towpath will remain open but there may be delays to move plant and equipment. 

To minimise disruption, our contractors will move out of the navigation whenever necessary to allow boating customers to pass.   Please be aware of increased activity and proceed with care, following any guidance from the staff on site.

You are welcome to contact us at enquiries.walessouthwest@canalrivertrust.org.uk or 03030 404040 if you would like to discuss this information with a member of our Customer Service Team.

Conditions can change. Check local signage and the latest official notice before travelling.

View original notice