Thu, Oct 15
Due to additional works that need to be carried out on the viaduct this closure has been extended to the 30th of November.
Ravensthorpe Towpath Closure TRU
Calder & Hebble Navigation
Type
Towpath Closure
Reason
3rd Party Works
Region
Yorkshire and North East
Last update
Thu, Oct 15
Wed, Nov 5 → Mon, Nov 30
Affected location
Calder & Hebble Navigation
Bridge 27, Ravensthorpe to Bridge 8, Forge Lane
Thu, Oct 15
Due to additional works that need to be carried out on the viaduct this closure has been extended to the 30th of November.
Tue, Sep 22
Due to additional works that need to be carried out on the viaduct this closure has been extended to the 31st of October.
Fri, Aug 14
The towpath closure has now been extended until 30th September due to safety measures required for ongoing works.
Wed, Jul 8
The towpath closure has now been extended until 31st August as working activities still need a closure in place to ensure safe operation of the viaduct construction.
Fri, Mar 27
A towpath closure is required to enable the Transpennine Route Upgrade works to proceed safely with a new viaduct construction at Ravensthorpe.
The towpath closure will be in place until the 31st July 2026. This is due to delays in the phases of working for the viaduct construction and the towpath needs to remain closed for safety reasons.
Please adhere to towpath diversion routes and Contractors instructions.
Tue, Sep 2
A towpath closure is required to enable the Transpennine Route Upgrade works to proceed safely with a new viaduct construction at Ravensthorpe.
Please adhere to towpath diversion routes and Contractors instructions.
Conditions can change. Check local signage and the latest official notice before travelling.