The towpath closure has now been extended until 31st August as working activities still need a closure in place to ensure safe operation of the viaduct construction.
Ravensthorpe Towpath Closure TRU
Calder & Hebble Navigation
Type
Towpath Closure
Reason
3rd Party Works
Region
Yorkshire and North East
Last update
Wed, Jul 8
Wed, Nov 5 → Mon, Aug 31
Affected location
Calder & Hebble Navigation
Bridge 27, Ravensthorpe to Bridge 8, Forge Lane
Wed, Jul 8
The towpath closure has now been extended until 31st August as working activities still need a closure in place to ensure safe operation of the viaduct construction.
Fri, Mar 27
A towpath closure is required to enable the Transpennine Route Upgrade works to proceed safely with a new viaduct construction at Ravensthorpe.
The towpath closure will be in place until the 31st July 2026. This is due to delays in the phases of working for the viaduct construction and the towpath needs to remain closed for safety reasons.
Please adhere to towpath diversion routes and Contractors instructions.
Tue, Sep 2
A towpath closure is required to enable the Transpennine Route Upgrade works to proceed safely with a new viaduct construction at Ravensthorpe.
Please adhere to towpath diversion routes and Contractors instructions.
Conditions can change. Check local signage and the latest official notice before travelling.