Birmingham and Warwick Junction Canal, Saltley, Birmingham

Navigation RestrictionActive

Birmingham and Warwick Junction Canal, Saltley, Birmingham

Birmingham & Warwick Junction Cnl

Type

Navigation Restriction

Reason

3rd Party Works

Region

West Midlands

Last update

Fri, Sep 12

Timing

Wed, Jun 11 → Sat, Oct 31

Affected location

Birmingham & Warwick Junction Cnl

Bridge 107, Gas Works to River Rea Overflow Channel Aqueduct

Update history

Fri, Sep 12

Short duration towpath closures and navigation closures may be required by the contractor between September 2025 and October 2026.   Craft using the canal may be instructed to wait for up to 30 minutes before continuing their journey through the area.   Please pass through the area with care.

Thu, Jun 12

BBV, a contractor working on behalf of High Speed 2 Limited, is undertaking works to construct a new railway viaduct over the canal. To carry out these works, the contractor has installed temporary sheet piling within the navigation, which reduces the width of the canal.

Short-duration towpath closures may be required by the contractor. Please pass through the area with care.

Conditions can change. Check local signage and the latest official notice before travelling.